14 Feb 2018 11:45 #1 by QuentinB
Hello,

Inside the "Today" menu, we find some reportings about tasks. Items in those reportings are colored (orange or red), depending on the remaining time. But, to be effective, the coloration needs an update of the tasks/actions/...
Even if the due date is past, if an item isn't manually updated, it won't be colored on those reportings.

Visuals indicators are quite usefull in those kind text's block. It should be great if this can be fixed.

Regards.

Quentin.

Please Log in or Create an account to join the conversation.

More
14 Feb 2018 20:51 #2 by babynus

Even if the due date is past, if an item isn't manually updated, it won't be colored on those reportings.

KIf indicators are not automatically calculated, it means the CRON process is not running.
Just launch it through admin screen.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
15 Feb 2018 09:51 #3 by QuentinB
Ho ! That's right, the cron job was stopped.

Thanks for the answer.

Quentin.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.