ProjeQtOr free project management software - The auto planning feature does not work when a resource is re-unassigned work - ProjeQtOr
 

The auto planning feature does not work when a resource is re-unassigned work

More
30 Apr 2018 08:32 #1 by NarayanAras
Reporting for v 7.0.2

I have the Auto-planning check box selected, as shown below.


In an experiment, I selected task-5 and deleted the resource, which was assigned at 100% rate.
I again added the same developer, and assigned 40 hours of work at 20% rate.
Then I saved the task.

Since the auto plan check box was selected, I expected the task to be recalculated automatically.
But this did not happen.
Finally I had to press the Calculate activities planning button manually.
The screenshot shows the final result.

Thus there is a bug in Pr5ojeQtor: The auto-recalculation checkbox does not work in some cases.
Attachments:

Please Log in or Create an account to join the conversation.

More
30 Apr 2018 11:50 #2 by babynus

In an experiment, I selected task-5 and deleted the resource, which was assigned at 100% rate.
I again added the same developer, and assigned 40 hours of work at 20% rate.

I tested, planning is recalculated after each update

Then I saved the task.

This has no impact (it should say "no change to update")

But take care : this check is active only when you see it !
It means only when you are on the planning screen...
Sure, user manual is not clear about that. We'll change this to be more clear.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
30 Apr 2018 15:14 #3 by NarayanAras
I will test this again, and revert.

@check box being active only when visible:
I am sorry, but I did not understand this caution.
I was on the same screen (but working in the lower half, where I can change the assignment).

Which are the other use cases when we are NOT on this page, and therefore the recalculation does not automatically happen?
Our PMs must understand this tip properly.

Please Log in or Create an account to join the conversation.

More
30 Apr 2018 17:00 #4 by babynus

Which are the other use cases when we are NOT on this page, and therefore the recalculation does not automatically happen?

If you are on screen Activity

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
02 May 2018 08:44 - 02 May 2018 08:55 #5 by NarayanAras
I checked this feature, and confirmed that it works fine.

However, during the testing, I noticed that tasks for a resource were overlapping. This was unusual, so I investigated by right-clicking on each task. I found that the resource (Akshath Hegde) was assigned 100% to each task, yet ProjeQtor split his daily hours among three tasks.

The screenshots below explain this situation:



So the question is, how exactly did ProjeQtor reduce the number of hours on a daily basis (from a constant 8 hours/day)?
Does this method ensure that these three tasks are finished in least amount of time? (Two of the three tasks were on critical path.)
Attachments:
Last edit: 02 May 2018 08:55 by NarayanAras.

Please Log in or Create an account to join the conversation.

More
03 May 2018 20:51 #6 by babynus
It may depend on assignment rate of planning mode.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.282 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.