The "Divide this assignment" does not work as expected

More
04 May 2018 08:25 #1 by NarayanAras
In an experiment, I started with this task:


Then I decided to split the work assigned to Akshath Hegde, by adding a new resource.
I pressed the button next to Akshath.

A window popped up, in which I specified a new developer.

I noticed that ProjeQtor had automatically assigned 15 hours of work to Sangeetha.
This was logical, because Akshatha was assigned 30 hours earlier.
I assumed that now Akshath is left with 15 hour of work.


But the final result shows that now Akshath is left with no work at all! [BUG#1]
The total hours for the task are reduced from 45 hours to 30 hours now. [BUG#2]
Attachments:

Please Log in or Create an account to join the conversation.

More
04 May 2018 10:35 #2 by babynus
Hi,

It seems result is not as expected when unit for work is "houré (works fine with "day")
Issue recorded as Ticket #3363

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.069 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.