Hello, I have exactly the same problem since the update of V7.0.9. Version V7.1.1 is not in question.
So I'm waiting like you a little patch that will provide a solution.
See you.
It is a lock issue : 2 users trying to update same item.
If transactions are long (many things to update on same operation) like on planning calculation, this may happen.
So if 2 project Leader plan 2 big projects at the same time, this may happen. On of the calculations can be an automated done (if enabled).
I've added an improvement on V7.1.2 to try and reduce transaction duration, starting transaction just before updates, at end of planning calculation instead of starting it at begining of calculation.... (Ticket #3426)
This may reduce locks.
If locks persits :
- try a cold restart of database
- try to calculate planning when no-one else in connected
this is very strange, i have some project with correct calculation planning, and other without !
I have close the projeqtor program, I'm alone connected.
I try to calculate planinig with just 3 activities open and it's failed!
Please help me because I have a meeting with Gantt update and I can't do it.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.