[SOLVED] Error when trying to modify or delete a function cost on resource

More
21 Sep 2018 09:04 #7 by louisc
Hi Pascal,

Thanks for the answer.
The workaround is working well.

One more question, how can we put dates in start and end dates ? So I could update the ressource cost when needed without impacting the past calculated costs.

Thanks !

Please Log in or Create an account to join the conversation.

More
21 Sep 2018 09:31 #8 by babynus
It is automatic.
When you enter first value for a given function, it is supposed valid alll the time.
When you enter next values for same function, start date is required, and previous value will automatically end at date - 1 day

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
21 Sep 2018 15:47 #9 by louisc
Ok that's clear, thank you !

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.