The difference with our context is that at the beginning, my real cost is not ok (yours is 100 for 1 day, and after 150 for 1 day).
Everything is ok, even before changing the cost.
My context is :
a project on which real work was already entered. But no cost on the function for the resource.
Then add a cost and no change
Cyril
The software is working well as you showed on the previous screenshot.
I can confirm that on project / activity that I have recently created or on which costs where added before real work allocation was saved in the tool.
My example is the following :
- ScreenShot 1 : On my project there is one activity that shows the following
210 days real work for my resource
Resource is assigned with expert function as you can see.
Real cost is 12 600 EUR
- Screenshot 2 : My resource cost is 504 EUR for Expert function.
Sorry you don't see the name of the resource on the screenshot but no doubt it's the resource that is assigned on the activity.
210 * 504 is 105 840 EUR, which is not 12 600 EUR.
So I don't understand why I get 12 600 EUR in real cost for the activity.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.