31 Oct 2018 14:53 #1 by beverley
Planning dates was created by beverley
Could someone explain to me the difference between planned, validated and requested dates and when/how each of these should be used.

Thanks Bev

Please Log in or Create an account to join the conversation.

More
31 Oct 2018 15:19 - 31 Oct 2018 15:21 #2 by alainforma
Replied by alainforma on topic Planning dates
HI
Planned : calculated by the application depending on constraints given: availabilities of resources, planning mode, left work...
Valided : dates that you will try to respect in agreement with your client ( or yourself) before or after recalculation, it depends on your strategy.
requested : just an indication on the customer's initial request ( no impact on calculation)

"when and how" depend on PM objectives, i suggest you firstly to read the user guide pressing f1 from dedicated screens

Regards.
Last edit: 31 Oct 2018 15:21 by alainforma.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.