I've change left work --> still have the project icon center white. (not orange)
Then i (re)calculate the planning --> still have the project icon center white. (not orange), no scheduled dates
Then I (re)change left work and (re)calculate the planning -->still have the project icon center white. (not orange), no scheduled dates.
New try today on another project.
Creating a new task then assigning a ressource (and charge) to this task.
Re calculate the project.
Still no scheduled dates.
(see the attached file)
Hi, Yes I did. I run it today but still same problem.
I've the same problem on differents projects. Same process to create project and task but on some task (not all) I have this problem.
1) Fix planning isn't checked on project (and on project on superior level).
2) WBS structure seems correct. But Consistency Check report oan error and the script is unable to repare it. (see pictures in attached files)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.