I would to propose an evolution about risk management, please correct me if I am missing anything or there's something I am wrong about.
When I create a risk I can input the cost of the risk (I input the mitigation costs, and I also input the end date considering the foreseen delay) but I can't see the impact on the planning of the project: if I originate it from a task (e.g. I have an activity going on that can be affected by external factors which could delay it) it could be useful to see the impact in terms both of costs and delay on the task itself.
Besides it could be useful to have a risk management plan like the it was requested with ticket #2540 (2016-0539).
I am aware of the difficulties of implementing such a feature (how am I going to decide whether the impact shall be shown on the gantt diagram or not? And in which percentage? With regards to the risk matrix, which result am I going to accept?) but it's a key feature missing in almost all project management tools available on the market, even proprietaries (and not cheap ones).
When I create a risk I can input the cost of the risk (I input the mitigation costs, and I also input the end date considering the foreseen delay) but I can't see the impact on the planning of the project: if I originate it from a task (e.g. I have an activity going on that can be affected by external factors which could delay it) it could be useful to see the impact in terms both of costs and delay on the task itself.
Maybe what you're looking for is provided through "global planning" view.
There you can define dependencies from risk to activity.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.