Hi,
At present time, in version 8.6.6 (sorry not being up-to-date, corporation constraint), planing calculation is based on workload as of some has been defined, otherwise on the duration. My use case is a mix between workload of resources in my firm, and a task duration defined by my subcontractor for which I don't know at this early stage the workload. I could separate into two tasks, but that's not convenient at all. If I could check a box to force the planning calculation to still use the duration, that would solve my problem. Moreover, later in the project, I will know the subcontractor workload and I will be able to switch to it more conveniently.
Best regards,
Alain
You just have to change planning mode to "fix duration".
Then resource with work won't be calculated "as soon as possible" but work will be dispatched over the duration (like regular between dates, but with floating dates)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.