I need to follow the following quality indicator on each of my projects:
QI = ((realWork + leftWork) /validatedWork) -1
It calculates the excess percentage of the project.
I do it each week then I save it to draw a graph and see the trend of my projects
Is it possible to add a screen which display the QI for each project with a button (one next to each QI) to save the QI associated to the current date?
Another solution would be to show the QI on project screen whith a button to save the current value with the current date.
The top would be to have a report with a graph showing the evolution of the QI per project. :cool:
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.