"Work hours" for each resource (like for calendar)

More
16 Jan 2014 11:06 #7 by ant740
" When you display work for all project in days, how is done conversion from hours to days for all resources ?"

"For instance, define work period of 8 hours a day.
Resource working 7 hours a day have capacity of 0,75.
Resource working 9 hours a day have capacity of 1,25, and a specific calendar with only 4 working days per week. "

==> it makes same thing than you propose to me
I've 1.25 days / day :)

Attachments:

Please Log in or Create an account to join the conversation.

More
16 Jan 2014 11:19 #8 by ant740
thanks for your help, your solution works perfectly !

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.