Define number of leaves for each resource

More
16 May 2019 12:16 #1 by srividhya
Hi,

Can someone please explain how to go about setting the number of leaves a resource can take in a year and accordingly plan the resource management.
I want to set 12 days a year, a resource can take a leave. Can this be done for all users? If so, how to do it?

Thank you.
Regards,
Srividhya
The following user(s) said Thank You: yalovali

Please Log in or Create an account to join the conversation.

More
16 May 2019 12:29 #2 by babynus
This can be done though HR management system, with Leave System.
Resources must be employees.
You define one or several contract types.
You define Leaves plan for each contract type.
You link each employee to a contract type.
That's all : yearly Leaves are automatically calculated.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.