25 Jul 2019 14:12 #1 by s.gelly
Task Status RollBack was created by s.gelly
Hello,

I've just started to use ProjeqtOr, and it seems to be a great product.

But as I'm a noob, I've clicked too many time on the bottom "status" on a task.

Is it possible to rollback the status to come back in "qualified" ?

Best regards.

Seb (and sorry for my english :) )

Please Log in or Create an account to join the conversation.

More
25 Jul 2019 14:17 #2 by babynus
Replied by babynus on topic Task Status RollBack
It is possible .. if your workflow allows it ;)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
25 Jul 2019 14:23 #3 by s.gelly
Replied by s.gelly on topic Task Status RollBack
thank you for your fast answer!!

ok I've seen the tab workflow but I didn't read how workflow work.

I'll see that and I'll be back!

Please Log in or Create an account to join the conversation.

More
25 Jul 2019 15:39 #4 by s.gelly
Replied by s.gelly on topic Task Status RollBack
It's working!! thank you very much! :)
have a good day

Seb

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.