We have been using Projqtor for timesheet input of real work.
Once a resource has already input Real Work on an activity is it possible to block input or to hide the acitivity in Timesheet screen so that the resource inputs no further Real Work on the activity?
In our specific case, the resource's contribution for the activity is concluded and we would not want for the activity to still be displayed on timesheet as this can lead to confusion and accidental inputs.
We have tried removing the Resource allocation from the project but the activity is still shown on Timesheet screen. Removing the resource's assignment to the activity is not possible.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.