Hello guys,
I created 2 tasks to make a test:
> Task A
> Task B with as successor of task A (End > Start + 5 days)
However in the planning view, the depedency does not apply (Please see attached)
Thanks for your quick reply, no there is no work recorded as I'm initializing the plan, so without work recorded the depedencies are not takken into account ?
Yes I put auto calculation of the planning.
The start date of the bar is displayed according to the 1st day with work recorded on timesheet. By adding a dependence (predecessor) with ( or without) a delay, the remaining days could be pushed back in time, the bar would grow longer (without any changes about the start date due to real work).
On planning screen view, even if the cell "automatic run plan" is checked, changes are not taken into account when data come from another screens. You have to enable the calculation. On the contrary, if you work directly on the planning view, every changes are taken into account when the cell is checked.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.