We are currently having an issue, here's the situation :
We have a collegue who badly entered his hours on an activity (he entered multiple days) this cause the entire planning (every next acitivtys) to be shifted because of this bad imputation.
This is very blocking for us
Because of the bad imputation my collegue entered,
The real time on this imputation is now 35,00 hours instead of 7
When whe are using the planning calculator the planified date changes because of that (in the example : 24/09/2019)
As you can see on the screenshot, we are unable to modify these values neither on the activity nor on the imputation.
Sorry if i'm not explaining very well, I'm doing my best but I'm not sure to understand everything either ...
Issue on planning is due to left 49h work.
You can set this to zero on activity screen.
No more work will need to be replaned so planned end date will be real end date, which is the laste date of input of work in Timesheet.
You must change real work on Timesheet screen.
If it is lock, it should be because Week is submitted or validated. Unvalidate / unsubmit the week to change data.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.