Resource not being assigned correctly

More
02 Oct 2019 12:22 #1 by jhoareau
Hello here,

I have a resource (me) assigned to a project.
This project contains activities on which this resource is assigned on.
The planning calculator does not calculate the duration correctly ; the activity is displayed inside planning per resource but with no duration for these activities.
When I look at the project planning, it does display the activity but for the day of today and with a duration of 1 day.
Screens below :
Affections of the resource "not working" :


Affectation of the differents resources on the project


Planning of the resource "not working"


Project planning


Example of an activity on which resource is affected on


Best regards,

Jordan
Attachments:

Please Log in or Create an account to join the conversation.

More
14 Oct 2019 10:01 #2 by babynus
Hi,

Check capacity of the resource.
If capacity is zero, planning won't work.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.076 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.