[SOLVED] steering charts performance indicator

More
26 Feb 2020 18:30 #1 by dep@eca.fr
what's the calcul of steering charts performance indicator ?

Please Log in or Create an account to join the conversation.

More
27 Feb 2020 09:27 #2 by alainforma
hello

on report / steering charts :
on ticket the calculation is real work / Estimated work. if > 1 the resource is working slower than expected, or estimation was too short or increased real work is going faster than increased estimation
if<1 the contrary
on activity : real work / assigned work same reasoning.