Pandemic working hours

More
17 Mar 2020 17:13 #1 by fathibn
Hello,
we are starting to work half day du to corona. How can I put this in the configuration screen on projeqtor ?
Attachments:

Please Log in or Create an account to join the conversation.

More
17 Mar 2020 17:30 #2 by babynus
Replied by babynus on topic Pandemic working hours
The best is to change capacity for resources : you can define periods for variation of capacity.
It's not the more quick, as you'll have to change every resource, but I don't see quickest way to change capacity for everyone in one step.

Babynus
Administrator of ProjeQtOr web site