Hi,
Sorry, please take a look again to screenshots and especially to picture called "Real_time_2.png".
Picture "Real_time_1.png.png" was sent to show you that planning is calculated only for activity that has "Real time > 0 ".
On real_time_1, you don't have planning, but display of real work.
So I guess your project is not correctly calculated for some reason.
Is it possible to have live chat or maybe via Skype, What's app ... ?
Not on free support on this forum.
This can be provided only to customers subscribing to our support service.
I'm sure there is something in your configuration that forbids planning calculation. This can be :
- fix planning flag on the project.
- allocation rate to zero : this must be controlled on the project and on parent projects, up to top level (the restriction on allocation rate is controlled on the whole hierarchy).
- assignment rate to zero
- capacity of resource to zero
- calendar with no oppen day