How can I calculate Schedule Variance and Effort Variance in the tool

More
14 May 2020 14:14 #1 by shobhana.mahanti@gmail.com
How can I calculate Schedule Variance and Effort Variance in the tool

Please Log in or Create an account to join the conversation.

More
18 May 2020 18:14 #2 by babynus
ProjeQtOr does not manage earned value yet.
But you can get project variance through report "S-curve chart".
You'll need to define a baseline (the reference for the variance) to have it work.

Babynus
Administrator of ProjeQtOr web site