10 Jul 2020 08:02 #1 by service.automation
Hi,

I'm facing the following.

I'm assigned to a task, but I can't feel my timesheet related to this task.

What should be wrong in my configuration ?

Many thnaks for your support,

Fred
Attachments:
The topic has been locked.
More
10 Jul 2020 10:19 #2 by Gautier
Hello,

I think you have in global parameter, section timesheet , parameter : display only handled tasks : YES.
That is why you can display only handled task. If you want see your activity, you have to change statuts of your activity to get handled checked.
Maybe change your status to assigned to in progress.
The topic has been locked.
More
10 Jul 2020 12:33 #3 by service.automation
Hi,

Correct !

Many thanks,

Fred
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.