Is there a way to assign a resource as an assignment to multiple activities at one. I have about 100 activities and I have replaced one of my staff and I would like to assign the new staff as an assignment to the 100 activities of the person that I fired. How do I do this instead of using the assignment feature on each individual activity.
Best way is to use the replacement of allocation feature.
Go to project, in allocation list click on "replace" button (withj two arrows crossing each other)
Then select new resource that will replace old one.
All assignments to old resource will be replaced with assignments to new resource.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.