Hello.
I made a project and also made some activities. I add needed time based on hours. But when i click on automatic planning, it determines one day for each activity, how ever it just needs 1 hours, it dedicated 1 day to it. What's wrong with it?
Project Management is rarely used to plan "1 hour" tasks.
This is mostly some production management, not project management.
When managing project, planning tasks 1 hour long will take more time to plane the project than to execute the tasks...
So duration is always calculated in days, never un hours.
But you can plan several tasks of 1 hour on the same day (as long as the resource has the available capacity)
NB : you your issue is due to dependencies, have a look at "non strict" dependency mode, in global parameters.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.