19 Nov 2020 11:33 #1 by BrunoF782
Hello,

i'm kind of stuck with an activity :



This activity has with 0.25 of work left. The manager of this task wants to close it, so he want's to get rid of the 0.25 left.

When editing the assignation, i can't find how to erase this time left. If i click on the 0.25 left it replaces it by a full day (This is what i've done in the capture).

Thanks for your help.
Attachments:

Please Log in or Create an account to join the conversation.

More
20 Nov 2020 08:50 #2 by babynus
You must go to the Timesheet and change left work to zero

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
23 Nov 2020 08:21 #3 by BrunoF782
thanks, it worked perfectly.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.