maximum execution time 120 sec

More
02 Feb 2021 12:28 - 02 Feb 2021 12:28 #1 by Julien Gahon
Hi,
Il need to close a ressource actually associated to more than 160 activites, so ProjeQtor need to close it at the same time. Unfortunatelly it doesn't apparently due to a kind of timeout. Please find attached the error message.

Could you please tell me how to solve that issue?

Thanks & Regards
Julien GAHON
Dietsmann
Attachments:
Last edit: 02 Feb 2021 12:28 by Julien Gahon.

Please Log in or Create an account to join the conversation.

More
03 Feb 2021 00:34 #2 by babynus
Possibly V9.0.3 brings performance improvement that will  reduce update time.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.