03 Feb 2021 14:33 #1 by Julien Gahon
Hi,

I need to close some activities in mass. I thought I could use the Import Data tool by putting "1" as closed value into an activity template, but it doesn't work.
Activities are actually "done".

How can I do that?

Thanks & regards,
Julien GAHON
Dietsmann

Please Log in or Create an account to join the conversation.

More
03 Feb 2021 15:14 #2 by Arkhanje
Hello

You can use the multiple update function in the toolbar of the list area(v9.0).
Launch the feature, a new screen is displayed.
On the line "change status to ..." choose closed
Save

Your activities are now closed.

Be careful, however, if your workflow has controls to be carried out! If a field becomes mandatory to move to another state, such as the result field to be completed, then these activities will not go into the closed state ! 

Enjoy !
The following user(s) said Thank You: Julien Gahon

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.027 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.