displacements ... Is there a way to enter the displacements? For example during the week there may be trips to collect aobjet or various appointments ... which are outside the project thank you
***
dépalcements...
y a t il une manière de rentrer les dépléacements ?
Par exemple dans la semaine il peut y avoir des déplacements pour récupération d'aobjet ou rdv divers ... qui sont hors projet
Hello,
just in case it can help : we use 2 tips to handle business trips and off-projects stuff :
1/ Create a type of activity «Déplacement», so it is easy to identify activities of the project that are realized in the customer premises for instance.
2/ Create a project dedicated to all «diverse» stuff and unplanned activities such as overhead (corporate meetings, ...) or external training, etc ...
manual planification or filing a line on timesheet screen which belongs to an administrive project type or the worst solution creating a meeting ( a special one as displacement )
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.