Planning with fixed milestones

More
18 Nov 2021 14:16 #1 by ueisenb
Hi all,
I've setup a project with a fixed milestone (=external deadline). I also setup a task which should be finished before this deadline. Hence I setup a end-start dependency between the task an the milestone. If the task takes longer such that it misses the deadline it looks like this after pressing the "planning" button.

The question: Is there a possiblity to get warning while planning (e.g. "dependency cannot be fullfilled")? Of ocurse I can maunally set a "validated end date" for the task to hit the milestone and the task becomes red if the date is is later than the validated one. However druing the initial planning I don't have this set. Thank you in advance for your help.

Best regards,

Udo Eisenbarth
Attachments:

Please Log in or Create an account to join the conversation.

More
23 Nov 2021 10:57 #2 by babynus
Hi,

It is subject of ticket #5243

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.050 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.