You can impact the planning by playing with the different planning modes.respecting constraints you gave.
In your case :
you can smooth the load between two dates: the planning will not necessarily be correct from day to day but it will respect your wishes.
You can use the fixed duration even if the follow-up with the work done on it for the planification is not very judicious (we cannot steer an activity at the same time by the load and by the duration if it is not by adjusting one to the other manually)
you can use the manual schedule by half day
Incidents are registered by tickets . Tickets can be linked to a "planning activity" dedicated for their resolution.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.