Hole in forecast assignement

More
22 Mar 2022 11:50 #1 by cmarti
Hello all,
I have just reconciled the complete planning of all projects and I have a strange gap on the assignment of some resources. It doesn't happen for all resources.
The attached picture shows this lag for resource 6

E.g. the activity 764 has no predecessor (only successors), is planned "as soon as possible", but the guy is not assign as soon as the previous activity (on another project) is done

What kind of trials can I do to understand where is the bad constraint?

Thank you for any help
Attachments:

Please Log in or Create an account to join the conversation.

More
25 Mar 2022 00:35 #2 by babynus
Poissibly because you replaned project from march 21st and users did not fulfill real work input for previous week.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.