Confusion in Duration concept.

More
22 Apr 2022 13:18 #1 by chandrashekhar
Hi Expert,

I can't understand about duration shown in planning. I have attached a screenshot. for reference. I am calculating duration=end date - start date.
i.e. for id=3 it is showing "164" (not considering both dates in the calculation)
      for id=17 it shows "20" (considering both start and end dates in the calculation).
      for id=286 it shows "1" (considering both start and end dates in the calculation).
      for id=1 it shows "-" 

Please give an understanding of my concern.

Note We have set off days (Saturday & Sunday).
I am using the xlsx file to find the duration (which is also attached for reference)
I have also attached global parameter screen for reference.

 
Attachments:

Please Log in or Create an account to join the conversation.

More
22 Apr 2022 14:32 #2 by alainforma
HI,

Have you thought to replan the planning ?

Please Log in or Create an account to join the conversation.

More
22 Apr 2022 14:51 - 22 Apr 2022 14:54 #3 by chandrashekhar
No, I was just observing progress %, planned work, left work, assigned work & I confused about duration column.
Last edit: 22 Apr 2022 14:54 by chandrashekhar. Reason: wanted to add more detailing.

Please Log in or Create an account to join the conversation.

More
22 Apr 2022 16:56 #4 by alainforma
You should, data could be refreshed.

Please Log in or Create an account to join the conversation.

More
24 Apr 2022 13:05 #5 by babynus
Duration is in "Open days" not in "Calendar days".
It removed all off days (week-ends and off days in default calendar)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
25 Apr 2022 08:17 #6 by chandrashekhar
Thanks, I know that duration is calculated using open day only & I am reaching near to solution but here in our Company it is only second and fourth Saturday off. Can We set the calendar in that way? If I can do so It will get exactness in duration.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.