No, it is not %, it is work in Days.
The default unit for work in projeqtor is days, and work data is always stored (in DB) in days.
So export is also in days.
I attached 2 files again. One file it is how I see estmated, real and left time for 2 tickets in PJ. And second file how I see tickets after exporting to csv.
Export is exactly how I explained, and I can guess you defined days with 8 hours per day.:
Ticket 7111 : estimated = 20 hours = 2,5 days, real = 0 hour = 0 day
Ticket 7061 : estimated = 14 hours = 1,75 days, real = 7 hours = 0,875 day
It is the values that are exported, in days (with rounding at 2 decimals)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.