I need your help on filling timesheet, can my all resources fill their timesheet for misc. activities, which are not connected to any recorded Projects in projeQtOr.
I mean, is it possible to create activities without creating project or please guide me a way to organize my purpose.
The activities are necessarily linked to a project. In fact, apart from the environmental parameters, all the elements related to the management of a project are necessarily linked to a project. Hence the fact that ProjeQtOr is a project organizer.
So no, nothing outside the projects, but nothing prevents your resources from charging to several activities of several projects if they are allocated to them!
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.