I am struggling with correct definition of our project I am importing to ProjeQtOr.
If they are not a bug solving projects, all our projects are defined in similar way - all have fixed effort estimate and fixed end date.
Assigned resources always have more than one overlapping projects active with not defined start dates but end dates.
Up to now I was not able to define project in correct way so they are planned with preserving both fixed values, the effort estimate and the end date. What ever I do, change or select, at least one of those values is changed. In most of the cases, when I change project parameter, its recalculation change planned effort estimate from defined one to much higher one covering whole period from start date to planned end date.
I know I am doing something wrong, our project definitions are nothing new and strange but am unable to find what is that .
Any suggestion and tip is very welcome.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.