Work - weekly not shows sum of real hours on the right of the report

More
18 Mar 2023 12:21 #1 by chandrashekhar
Hi there,

We are having 22 projects (including HR module and maintaining leaves) and scheduled a report: reports>real work>work>work weekly.
When we check report on screen, it shows ok, but when we see with using "export to pdf format" or one we are receiving in mail, it is not showing full report there in PDF file.
Is there any way that I can see this report with full information. Currently it is being not displayed sum of hours on the right side of the report for each resources.

Please refer attachment
Attachments:

Please Log in or Create an account to join the conversation.

More
20 Mar 2023 09:27 #2 by babynus
If there are many projects, the columns may not be able to shrink to be able to display the whole table on the page.
Difficult to do better.
Possinly you can try to print / exoirt to pdf to get better reult.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.027 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.