I have one project with 2 activities, one activity has a cost to 100$ for exemple, the project's cost is 100$ (Sum of all activities).
If I reset the activity's cost to 0, the project's cost isn't reset to 0.
It's a bug or I miss an action ?
No, it's not a bug, it's expected design.
If project has no activity (for instance only tickets) then cost is entered manually.
If project has activities, cost for project is sum for activities.
If you remove the last activity, you get back to the last case : cost manually entered, the the cost of last activity is concidered as project cost.
This may seem weird for project, but concider it's the same algorythm for activities, if an activity has sub activities, ...
Hello,
If you really want to reset the project cost, you may need (connected as an admin) to modifiy an option in : Global parameters/Planning/Automation
You need to set "consolidate validated work & cost" to "Always" (because of what Babynus explained just before).
See the screen below.
Then, re-enter the cost of 100 on your activity, save. Enter 0, save. Your project cost will be correct (it will sum the cost on other activities, etc.)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.