I have a problem when planning a task. I have a task that lasts 1 year. Every month I want to plan 2 days for this task. However if in reel time (in the timesheet) I end up not spending 2 days, but 1 for example I don't want the remaining day to "transfer" to the next month when I recalculate my planning. I cannot put "0" in the "left work" because I still have work to do during the coming months. In other words, whatever the time spent in the past, I don't want the future months to be impacted and I want to keep only 2 days per month of work. Do you have a solution ? What planning mode should I use?
Best is "recuring" planning mode.
But this is planned on a weekly basis.
So you can plan 0.5 every monday, for instance, it will be about 2 days per month.
And it will behave exactly as you expect
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.