In the resource planning, planned workload are unexpectedly starting today which is not in line with the activity planning. I want the resource planning to be synchronized with the activity planning in order the same task starts and end at the same date. I assume there is a configuration checkbox somewhere in the options, but I cannot find it.
Well, in fact resource planning has exactly the same source as Activity planning.
This means that if all you tasks begin Today in Resource Planning view, they will also begin Today in Activity Planning view.
Possibly you just recalculated the planning from Today...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.