Whilst, the documentation says that each resource is attached to a calendar to define its working days,
I am unable to create a specific calendar with Saturday and Sunday as working days (they are greyed out)).
I have one resource 7/7 24h/24h.
So that you can make a 24/7 calendar you need to go to the global parameters to indicate that weekends are potentially working days.
Be careful, however, with other calendars where you will have to check off these two days so that they are recognized as non-working.
When activity has no assignement (for instance fix duration tasks), duration is calculated from Project Calendar.
When activity has assignment with assigned work, duration is calculated from Resource calendar.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.