26 Jan 2024 11:56 #1 by jul
I cannot find where to configure the FTE. If I specify tasks in hours, this must be known.
Anybody can help ?
Thank you !

Please Log in or Create an account to join the conversation.

More
26 Jan 2024 12:48 #2 by tblanken
Have a look at Environment -> Resources

Best regards,
Torben

Please Log in or Create an account to join the conversation.

More
26 Jan 2024 13:48 #3 by jul
This is the resource management page, where I can specify the FTE for a given resource. What I am looking for is some configuration mapping 1 FTE to a number of hours.

Please Log in or Create an account to join the conversation.

More
26 Jan 2024 13:50 #4 by tblanken
Configuration -> Global Parameters : Work time
The following user(s) said Thank You: jul

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.