Notification rules

More
22 Mar 2024 11:31 #1 by CSO_Arnaud
Hi,
I have a question about the notification rules,
I created a very simple rule on tickets. Comparison of two dates.

${date1} < ${date2}

I notice that the notification is activated even though my dates are equal
date1 : 16/03/2024 (15h35)
date2 : 16/03/2024 (15h35) 

This seems wrong to me, any idea?
Regards 

 

Please Log in or Create an account to join the conversation.

More
26 Mar 2024 15:15 #2 by babynus
Replied by babynus on topic Notification rules
If your date is a dateTime format, it compares dates with seconds, even if they are not displayed.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.