08 Apr 2024 14:57 - 11 Apr 2024 17:09 #1 by froutier
Hi,

I wish to allow my coworkers to mark some days as teleworking to share with the team.

I am not sure what the best practice would be for that. I am thinking of using a special task within an "internal project", with manual planning, and use the interventions feature.
But wouldn't that mark the resource as occupied ?
What is the best practice to handle a teleworking status, without impacting the availablity of a resource ?

Thx
Franck
Last edit: 11 Apr 2024 17:09 by froutier.

Please Log in or Create an account to join the conversation.

More
11 Apr 2024 11:44 - 11 Apr 2024 11:44 #2 by Arkhanje
Hello

But wouldn't that mark the resource as occupied ?


no, you can indicate intervention methods without planning work on these dates.

What is the best practice to handle a teleworking status, without impacting the availablity of a resource ?

For the moment, this is the only solution that is possible.
Last edit: 11 Apr 2024 11:44 by Arkhanje.
The following user(s) said Thank You: froutier

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.024 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.