Planning mode automatic fill the Timesheet

More
05 Jul 2024 16:11 #1 by silvia
Good morning,
for many projects/activities we are using the "manual planning" functionality that allows a manager to allocate in advance the time of his resources.
What we realised is the following: if the allocation is still in the future, the Timesheet shows a small number of the left-top corner suggesting the number of hours indicated in the "manual planning"; if the allocation results in the past (as the time has passed), the Timesheet is automatically filled with the value assigned in the "manual planning".

Is this the expected behaviour? Is there a way to keep always the "manual planning" as a suggestion in the Timesheet and not as "done work"?

Thank you very much,
Silvia

Please Log in or Create an account to join the conversation.

More
05 Jul 2024 20:34 #2 by babynus

Is this the expected behaviour?

Yes, absolutely

Is there a way to keep always the "manual planning" as a suggestion in the Timesheet and not as "done work"?

No, not with Manual Planning, but you may try another planning mode.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: silvia

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.