On a project where tickets are the driving concept, I have been careful that each ticket is linked to an activity.
However, these two reports ("Work detailed by resource" & "work detailed by activities") show different results, although they should just be different view of the same work.
Some work seems to be excluded from "work detailed by activities".
In my example, it seems that time affected to (periodic) meetings is not included in this report, while it is in "Work detailed by resource".
Is this expected or a bug ?
If it is expected, why, or is there a workaround ?
It is as expected.
"work detailed by activities" only includes work on Activities (as written on report title) and not work on Meetings or Test Sessions
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.