[SOLVED] Automatic assignation in activity from Kanban

More
16 Jan 2025 11:29 #1 by Yannobi
Hi,
I'm on a 11.2.2 version

I activated the option "when i affect a responsible to on activity, he become as well assigned with the expected working time. It's works perfectly on the activity list.

My issue appears when i use kanban. When a member drag a card on the column "en cours", a window ask for the responsible. When the member select his name, he become responsible but he is not assigned to the activity.

If i select "modify" on the contextual menu of a card, and i select the responsible, it's ok and the responsible become assigned as well.

Is there here a limitation or a bug ? Thank you for your help

Please Log in or Create an account to join the conversation.

More
16 Jan 2025 17:17 - 17 Jan 2025 15:03 #2 by Yannobi
Ok, I found it !

I had to change some habilitation

 
Attachments:
Last edit: 17 Jan 2025 15:03 by babynus.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.