Inquiry About Task Scheduling in ProjeQtOr

More
24 Feb 2025 11:09 #1 by ZERELLI
Hello,I have a resource that needs to work on two different projects, A & B, alternating every other week. The first week is dedicated to Project A, and the second week to Project B.The workload associated with an activity for this resource may exceed 5 days, meaning that in terms of duration, the activity will extend over more than two weeks (e.g., Weeks 1 and 3).Additionally, the goal is to ensure that any potential delay impacts only the relevant project.Is there a way to configure the resource allocation and task scheduling to achieve this behavior?Thank you in advance for your help.

Please Log in or Create an account to join the conversation.

More
25 Feb 2025 10:37 #2 by Arkhanje
Hello,

the question would take a lot of time and lines on the forum, that's why this kind of information is covered in planning training.
You can try to take a look at the manual . (F1 in the application)
You will have the operation of the different steering levers, such as planning modes , allocation and assignment rates for example and all about resource management

Or you can also participate in one of our training courses! 

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.