I'm currently learning the software's features, and sometimes I don't understand certain things.
In this case, I'm entering actual hours related to activities for one of my colleagues. However, while everything worked correctly up to now, I'm now unable to enter their hours between two dates. The time entry boxes have disappeared, replaced by a table where the boxes are not fillable.
Is this a ProjeQtOr feature I haven't understood, and if so, which one?
Several things can prevent allocations from being populated.
Either the period was validated with timesheet validation.
Or the month was blocked by monthly consolidation.
Or a global parameters option or the planning mode used doesn't allow timesheet to be populated before a certain date.
Or your rights to view and modify allocations for other resources have been revoked.
More information is needed to really know what's going on.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.