View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How to give Subtask creation access to Project Members - ProjeQtOr
 

How to give Subtask creation access to Project Members

More
05 Apr 2025 18:40 #1 by ajay-gewan
I want my Project Members to create Sub Tasks only under the tasks they are responsible for. I tried to update the Access Modes value to "Own Elements" under Create but nothing happened. Am I missing something??

Please Log in or Create an account to join the conversation.

More
08 Apr 2025 09:29 #2 by Arkhanje
Hello

That's not going to be possible. The rights you distribute cannot be implemented. The elements for which they are responsible and their own elements cannot be applied to creation rights. If they can create sub-activities, then they must be able to create activities.

Perhaps the best option would be to give them access to the todo list , which would allow them to break down an activity into sub-tasks to be completed. They can be tracked with flags such as in progress, done, and closed, a manager, and which offers a dedicated screen in addition to a section on the activities screen.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.046 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.