I want my Project Members to create Sub Tasks only under the tasks they are responsible for. I tried to update the Access Modes value to "Own Elements" under Create but nothing happened. Am I missing something??
That's not going to be possible. The rights you distribute cannot be implemented. The elements for which they are responsible and their own elements cannot be applied to creation rights. If they can create sub-activities, then they must be able to create activities.
Perhaps the best option would be to give them access to the
todo list
, which would allow them to break down an activity into sub-tasks to be completed. They can be tracked with flags such as in progress, done, and closed, a manager, and which offers a dedicated screen in addition to a section on the activities screen.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.